    Though the Rs.45 cr government project is stated to be completed in two years, the problems in acquiring private properties lead to delay in completion beyond five years. Consequently there is a cost overrun and the private contractors who invested money in the project faced huge financial losses.

    Which of the following can be concluded from the above?

    Options :-

    1. Completion of all prerequisites, including acquisitions of property before awarding the contracts, can avoid financial losses
    2. No property owner likes to part with his/her property
    3. Ownership of property is a legal right but not a fundamental right
    4. Government should plan projects in a way that does not require acquisition of private properties
    5. Government has the authority to acquire private property for public use
    Post your Training /Course Enquiry
    Are You looking institutes / coaching center for
    • IIT-JEE, NEET, CAT
    • Bank PO, SSC, Railways
    • Study Abroad
    Select your Training / Study category
Reply To: Though the Rs.45 cr government project is stated to be completed in two years, the problems in acqui….
Your information:




Verify Yourself




Log in with your credentials

or    

Forgot your details?

Create Account