    Ramos, Karen and Vincent take a contract to do a piece of work. Ramos can do it alone in 10 days. Karen can do it in 20 days and Vincent can do it in 40 days. They work alternately. On the 1st day, Ramos will do it alone, on the 2nd day, Karen will do it and on the 3rd day, Vincent will do it alone, and so on till the work is completed. Find the time taken to complete the work.

    Options :-

    1. 12.5 days
    2. 13.5 days
    3. 14.5 days
    4. 16.5 days
    5. 17.5 days
    Post your Training /Course Enquiry
    Are You looking institutes / coaching center for
    • IIT-JEE, NEET, CAT
    • Bank PO, SSC, Railways
    • Study Abroad
    Select your Training / Study category
Reply To: Ramos, Karen and Vincent take a contract to do a piece of work. Ramos can do it alone in 10 days. Ka….
Your information:




Verify Yourself




Log in with your credentials

or    

Forgot your details?

Create Account