    Mahesh and Umesh can complete a piece of work in 10 days and 15 days, respectively. Umesh starts the work and after 5 days, Mahesh also joins him. In how many days will the work be completed?

    Options :-

    1. 7 days
    2. 9 days
    3. 11 days
    4. None of these