    It has been estimated that a minimum run-off of approximately 94 m3/sec will be available at a hydraulic project with a head of 39 m. The efficiency of the plant is 80%. The firm capacity of the plant is

    Options :-

    1. 25500 kW
    2. 28770 kW
    3. 42424 kW
    4. 17882 kW