    In a network, the optimistic, most likely and pessimistic times (in weeks) are shown for each activity, in the order given in the brackets. What will be the expected completion time and the variance of completion time, respectively for this network?

    Options :-

    1. 25 weeks, 1.632
    2. 27 weeks, 2.444
    3. 28 weeks, 2.92
    4. 26 weeks, 2.92