    Four men can dig a pit in 15 days. A man is 1.5 times more efficient than a boy. What will be the number of days taken by 8 men and 6 boys to complete the same work?

    Options :-

    1. 6 days
    2. 10 days
    3. 7 days
    4. 5 days
    5. 12 days