    Four jobs a,b,c,d are there with their respective deadlines 2,1,1,1 The associated profits with them are 20,10,40,30 respectively. Sequence the jobs in order to get the maximum profit. Find the absolute difference of profit earned by completing the jobs and penalty for left out jobs _____________.

    Options :-