Consider the following average operating data for conventional activated sludge treatment plant at Kozhikode.Waste water flow = 35000 m3/day
Volume of aeration tank = 10,900 m3
Influent BOD = 250 mg/lit
Effluent BOD = 20 mg/lit
Find out the aeration period.Options :-
- 750 hrs
- 7.5 hrs
- 0.75 hrs
- 7.5 days