    A contractor agreed to complete a work in 90 days. He engaged 48 men for the work and after doing the work for 50 days he came to know that three-fifths of the work has already been completed. How many men should he remove to finish the work in the agreed time?

    Options :-

    1. 4 men
    2. 8 men
    3. 6 men
    4. 10 men