    ‘A’ can do a piece of work in 18 days. If ‘B’ joins him and they work on alternate days starting with ‘A’, the work will be completed in 24 days. How many days will ‘B’ take alone to complete the work?

    Options :-

    1. 12 days
    2. 18 days
    3. 24 days
    4. 36 days
    5. 40 days