This topic contains 0 replies, has 0 voices, and was last updated by  EduGorilla 2 years ago.

  • Author
    Posts
  • #730957 Reply
     EduGorilla 
    Keymaster
    Select Question Language :


    ‘A’ can do a piece of work in 18 days. If ‘B’ joins him and they work on alternate days starting with ‘A’, the work will be completed in 24 days. How many days will ‘B’ take alone to complete the work?

    Options :-

    1. 12 days
    2. 18 days
    3. 24 days
    4. 36 days
    5. 40 days
    Post your Training /Course Enquiry
    Are You looking institutes / coaching center for
    • IIT-JEE, NEET, CAT
    • Bank PO, SSC, Railways
    • Study Abroad
    Select your Training / Study category
Reply To: ‘A’ can do a piece of work in 18 days. If ‘B’ joins him and they work on alternate days starting wit….
Your information:




GET UPTO 50%    OFF!
Verify Yourself




Log in with your credentials

or    

Forgot your details?

Create Account