    A can complete a job in 6 hours, but B takes 8 hours. They work together for 2 hours and A leaves the job. How long will it take for B to finish the job?

    Options :-

    1. 6 hours
    2. 4.66 hours
    3. 3.5 hours
    4. 3.33 hours
    5. 2.5 hours