A, B and C can complete a work in 8, 16 and 24 days respectively. They start the work together and A works till least moment. If C leaves the work 2 days before and B leaves the 1 day before completing the work, in how many days the work will finished.
Options :-
- 5 days
- 4 days
- 8 days
- 3 days