    24 men can complete a work in 16 days. 32 women can complete the same work in 24 days. 16 men and 16 women worked for 12 days. How many more men are required to complete the remaining work in 2 days?

    Options :-

    1. 24
    2. 36
    3. 32
    4. None of these